LKCo
   
Lee Kennedy Co Inc  
Building Partnerships
<< back to FasTrack
page:    1   2    3    4      
   








   


Fall 2002

A Tight Squeeze
Construction Methods for Building on a Confined Site


The only construction access to the site is through a narrow alley.

 

 


The Center will house theaters,
studios, seminar rooms and offices.

 


An angled glass wall makes a unique backdrop for the lobby of Theater 1 on the second floor.

 

 

The city of Boston entertains a long history of utilizing its limited available space to maximum capacity, and the structures dotting today’s skyline are more complex and completed quicker than ever before. As the demand for new construction increases–and available land decreases–owners, designers and general contractors need to be extremely resourceful in order to overcome the challenges presented by Boston’s increasingly tight conditions.

The construction of Emerson College’s Tufte Performance & Production Center (TPPC) in Boston’s Theater District is a prime example of the planning, skill and finesse necessary to complete a project within the confines of a tight building site. The 10-story Tufte Performance & Production Center, which features an “L-shaped” footprint, will be bounded on four sides by existing structures. Furthermore, the only construction access to the site is through narrow Allen’s Alley off Tremont Street.

The TPPC, designed by Elkus/Manfredi Architects ltd., will be bounded on the north and west sides by the Walker Building, on the south and west sides by the State Transportation Building and on the east side by the Emerson Majestic Theatre. The TPPC's public entrance will be on Boylston Place where it will connect to a lobby in the Walker Building as well as at the fifth and sixth floors of the Walker Building. The TPPC will also connect to the Emerson Majestic Theatre at the stage house, and to an egress corridor in the State Transportation Building.

Lee Kennedy Co. performed extensive preconstruction services to plan an effective solution to the project’s logistical challenges. In addition to diverting traffic, equipment, utilities and operational functions out of the alley so that construction could start, the preconstruction process enabled Lee Kennedy Co. to secure permits more easily as the result of early, ongoing discussions with the respective agencies. “The site not only required City approvals, but State approvals as well,” notes Senior Estimator Peter Doran. Because the TPPC abuts the State Transportation Building, State agencies were also involved in the permitting process. A detailed Construction Management Plan was developed to clarify the intent of the project and provide the numerous permitting officials a comprehensible picture of the work to take place.
“Innovative building techniques are necessary to accommodate a tricky site like this,” says Steve Keith, project executive for the TPPC project. An example of such techniques is the placement of the tower crane. “There’s so little space to work with, that we incorporated the crane right into the footprint of the building,” comments Steve.

“In addition to overcoming the physical confinements of the site,” adds Project Manager Anthony Dirubbo, “developing a solid construction schedule was necessary to ensure the project would run properly.” Because the only means for getting materials and equipment to the site is through the alley, measures were established early to assure that all parties would have pre-planned access to the alley as needed. Plus, Tremont Street is currently host to several construction projects, which means the ability to cue trucks on the street is limited and the schedule must accommodate these restrictions. Since the site is on an urban campus setting, heavy pedestrian traffic flow must also be taken into consideration.

As with any construction project, sensitivity to neighboring buildings and tenants is always a concern. In the case of the TPPC, it is particularly important because access is extremely limited to the adjacent properties. “In order to minimize disturbance,” notes General Superintendent Chris Pennie, “careful lines of communication were established so that any issues could be handled promptly.” Furthermore, because heavy construction will be taking place within the closest possible proximity of the abutters, an extensive survey of existing conditions was performed which allows Lee Kennedy Co. to handle any issues that could arise as a result of construction.

When completed, the TPPC will house two theaters, two television studios, design studios, seminar rooms, a control room, faculty offices and a full array of facilities to provide a complete home to the School of the Arts. Additionally, the TPPC will contain support spaces for the Majestic Theater and a service court for all the surrounding buildings. The TPPC will be completely wired for phone and data, which is connected to the campus data system. All services–particularly the HVAC–will be carefully constructed to substantially eliminate noise and comply with the stringent acoustical needs of the building’s theaters. Construction is slated for completion in the spring of 2003.


page  1  2  3  4   : :  next >>

<< back to FasTrack

 

 

     

questions or comments?
e-mail us.

 
© 2002  Lee Kennedy Co., Inc.