| |
|








|
|
|
|

Spring 2003
Project Update
A Super-Sized Effort
|
| | |
|

|
The new Shaw's in The
City flagship supermarket at the Prudential Center
is remarkable for its aesthetically pleasing design. Customers
will be sure to take note of the store's glass rotunda entryway,
rooftop courtyard, and meticulously executed facade designed
by CBT/Childs Bertman Tseckares Inc. What they are less likely
to consider are the extraordinary measures that were necessary
to ensure that the structure be built at all! The footprint
of the building sits partially over the Prudential Center
garage and partially over the Massachusetts Turnpike, on a
site abutting three busy streetsHuntington Avenue, Ring
Road and Exeter Street. Thus, enormous amounts of strategy
and forethought were required on the part of Lee Kennedy Co.
in order to facilitate both conformity with city regulations,
and the sort of logistical maneuvering necessary to build
such an ambitious structure in such a constricted space. Two
levels of parking were removed in order to accommodate a new
loading dock accessible from Exeter Street, which, due to
loading restrictions, was also used to house the crane. The
two parking levels directly beneath the crane were shored
up to support its weight. Careful scheduling and strategic
planning ensured that work along the perimeter of the building
be completed over a series of weekends, as permitted by the
City. Construction of the store's interior, designed by Edwards
and Kelcey, began last spring and overlapped with base building
construction. All in all, this truly was a project fit for
the Jumbo Aisle!
Project Team:
Lee Michael Kennedy, project executive;
Ryan Klebes, assistant project manager; Jim Callahan, superintendent
|
| |
| A Window to the
Future |
| | |

|
High-end technology met artful design in the
construction of office space for the financial firm Atlas
Venture Inc. In order to protect and maintain the company's
information network, three uninterrupted power systems (UPS)
were installed and a 5-ton chiller was mounted to the roof
to cool the computer room, which also included a pre-action
fire protection system. Further accommodation of the company's
technological needs was achieved through the construction
of a video-conference room featuring a concealed projection
screen. These forward-looking foundations, designed by Solomon
+ Bauer Architects Inc., were then dressed in suitably modern
clothing: floor-to-ceiling glass-front offices were built
on the perimeter of the space, and sandblasted, contemporary-style
glass panels were installed in the conference rooms and reception
area. As this was a project involving much glasswork and many
windows, it seems fitting that Lee Kennedy Co. removed an
outer window and made deliveries through the opening in order
to minimize disruption to other tenants in the building. LKCo
is always on the lookout for that perfect window of opportunity
to ensure that a job runs smoothly!
Project Team: Eugene
Kennedy, project executive and Bob Hogan, superintendent
|
| |
|
Writing the Book on Restoration
| |
| | |
 |
When architect Charles Follen McKim and painter
John Singer Sargent collaborated at the turn of the twentieth
century on the design of a stunning gallery for the Boston
Public Library, they were unaware of the fact that,
almost a century later, their collaboration would broaden
to include a new participant: Lee Kennedy Co. After an award-winning
performance for Phase IIA of the McKim Building Restoration,
LKCo has again teamed up with architects Shepley Bulfinch
Richardson and Abbott to complete Phase IIC, which involves
the meticulous restoration of this historic gallery. The series
of murals painted by Sargent in the gallery between the years
of 1895 and 1916 is being reconditioned, and the surrounding
sandstone walls cleaned, using a new micro-abrasive technique
designed to protect soft surfaces. In order to showcase the
murals in their revivified glory, and to honor the wishes
of the gallery's designers, three large skylights that had
been covered for years are being opened once again - with
the modern innovation of photo-cell operated sunshades to
prevent UV damage to the murals.
Restoration work is also being completed in
other areas of the McKim Building. Woodwork and terrazzo flooring
is being restored in the Webster Room, and the walls and ceiling
of the Cheverus room are being re-plastered. The Changing
Exhibits Room will be outfitted with a new marble floor, and
will also benefit from some plaster repair. While all of these
tasks are being completed, painstaking consideration is being
given to the protection of the historic elements of the building.
Temporary tents have been erected to enclose LKCo's workers
in order to minimize disturbance to surrounding areas. The
project is slated for completion in the fall of 2003.
Project Team: Bob
OLeary, project executive; Sal Sachetta, project manager;
Jack Maunsell, superintendent
| | |
| Preparation Pays
Off |
| | |
 |
Lee Kennedy Co.'s Preconstruction Department,
one of its most distinguishing assets, was key to the success
of the construction of a four-story academic building for
Simmons College at One Palace
Road. Plans for the structure included
three levels of below-grade parking well below the water table,
requiring a deep excavation with an earth retention system
that provided a water cut-off. LKCo's Preconstruction Department
explored the options, and successfully selected a system ideally
suited to the site and its surrounding properties. Once the
project was underway, additional planning and forethought
were necessary in order to maintain an aggressive schedule
with overlapping design and construction activities.
The building, designed by Goody Clancy and Associates,
Inc., houses over 10,000 square feet of academic space, 11
electronic classrooms and over 200 parking spaces. If the
students walking its halls all took a lesson from LKCo's commitment
to preparation, there would be absolutely no cramming for
exams!
Project Team: Ed
Hines, project executive; Marc Buchan, project manager; Don
Cook, superintendent
|
| |
|
page 1 2
3 :
: next
>>
<< back
to FasTrack
|